57 stone price per yard commonly falls around $55-$105 for the stone itself, or roughly $90-$180 per cubic yard when delivery and spreading are included. The final quote depends on local aggregate prices, the amount ordered, delivery distance, and whether the site needs extra preparation.
| Item | Low | Average | High | Notes |
|---|---|---|---|---|
| 57 stone, material only | $55 per cubic yard | $75 per cubic yard | $105 per cubic yard | Bulk purchase; varies by market |
| Delivered stone | $80 per cubic yard | $120 per cubic yard | $190 per cubic yard | Includes typical local delivery |
| Delivered and spread | $110 per cubic yard | $145 per cubic yard | $220 per cubic yard | Accessible area and straightforward placement |
| Small load | $150 total | $250 total | $400 total | Supplier minimums and trucking drive cost |
Assumptions: U.S. bulk pricing for standard crushed limestone or comparable aggregate; local quotes may differ.
What a cubic yard of #57 stone usually costs
#57 stone is a graded crushed aggregate commonly used for drainage, driveways, and construction bases. A cubic yard of loose stone typically weighs about 1.3-1.5 tons, so suppliers may quote by the ton rather than by volume. At $35-$70 per ton, the material works out to about $46-$105 per cubic yard before delivery.
A practical average budget is about $75 per cubic yard for stone alone and $120 delivered. These figures assume a bulk order of several yards, standard stone, and a nearby quarry or landscape supplier. A small order may cost more per yard because truck and loading charges are spread across less material.
Installed pricing is higher when a crew unloads and spreads the aggregate. Basic spreading on a prepared, reachable area often adds $20-$60 per cubic yard, while excavation, grading, or hand placement can add substantially more.
How stone, trucking, and spreading shape the quote
Ask whether the quote is priced by the ton or cubic yard and whether taxes, delivery, and placement are included. The following ranges are typical planning figures, not fixed national rates.
| Quote component | Low | Average | High | Pricing basis |
|---|---|---|---|---|
| 57 stone | $35 | $50 | $70 | Per ton |
| Local delivery | $40 | $75 | $140 | Per truckload |
| Spreading labor | $20 | $38 | $60 | Per cubic yard |
| Site preparation | $0 | $15 | $50 | Per cubic yard, where needed |
| Small-load or minimum fee | $25 | $75 | $150 | Per order |
Delivery and minimum-load charges can outweigh the stone price on a one-yard order. Spreading rates assume basic placement by a crew; grading, fabric installation, or removing old material should appear as separate quote lines.
Why ton conversion and depth change the yard price
Volume estimates can be misleading if the supplier uses weight-based pricing. Stone density varies with rock type, moisture, and how loosely it is loaded; use the supplier’s conversion rather than assuming every yard equals the same tonnage. At 1.3-1.5 tons per yard, a $50-per-ton stone price translates to roughly $65-$75 per cubic yard.
Depth determines how many yards the project needs, often more than small differences in the per-ton rate. One cubic yard covers about 108 square feet at 3 inches deep, 81 square feet at 4 inches, or 54 square feet at 6 inches. Irregular ground and compaction can affect the actual amount required.
For example, a 500-square-foot area at 3 inches needs about 4.6 cubic yards before allowing for uneven ground. Ordering roughly 5 yards may be reasonable, but the appropriate depth depends on the use: a decorative drainage layer and a vehicle-access driveway may require different specifications.
Where regional quarry and trucking rates diverge
Prices tend to be lower near quarries and in areas with several competing aggregate suppliers. Remote locations, dense urban delivery routes, and markets with limited local stone can raise delivered quotes. As a planning comparison, urban or remote deliveries may run 10%-30% above a nearby suburban or quarry-area quote; rural pricing may be lower for material but higher for long-distance trucking.
Compare delivered totals rather than material-only rates when checking suppliers. Two quotes can differ by $20 per ton yet end up close after truck fees, minimum loads, and unloading conditions are counted. Ask if the delivery price changes by mileage, truck size, or whether the truck can reach the drop point.
When a short load or difficult access adds fees
Many suppliers set a minimum charge or require a minimum tonnage, so ordering one or two yards can carry a disproportionate delivery cost. Typical delivery fees range from $40-$140 for a local truckload, with short-load fees of $25-$150 in some markets. These charges vary by supplier and may be bundled into a delivered price.
Restricted access can turn a standard drop into a higher-cost placement job. A truck that cannot reach the work area may require a longer wheelbarrow route, smaller equipment, or separate hauling. Confirm whether the truck can unload where needed and whether driveway weight limits, gates, overhead wires, or soft ground create added work.
Three #57 stone orders with different delivered totals
These examples show how order size, delivery, and labor affect a quote. They assume common local rates and do not include major excavation or taxes.
| Project | Stone and quantity | Delivery and labor | Estimated total |
|---|---|---|---|
| Small drain strip | 2 yards at $75 = $150 | $100 delivery; $80 spreading | $330, or $165 per yard |
| Prepared garden area | 5 yards at $70 = $350 | $85 delivery; 3 labor hours at $45 = $135 | $570, or $114 per yard |
| Driveway section | 10 yards at $65 = $650 | $110 delivery; 6 labor hours at $50 = $300 | $1,060, or $106 per yard |
Larger orders often lower the delivered cost per yard, but site work can erase that savings. The labor figures represent basic spreading, not excavation or extensive grading.
How to lower a delivered #57 stone bill
Measure the area and choose the intended depth before requesting quotes. A clear square-footage estimate helps prevent overordering, while an overly thin layer may require another delivery later. Ask suppliers to confirm the ton-to-yard conversion and state the quantity in both units where possible.
Compare at least three itemized quotes for the same stone, quantity, and drop location. Ask whether combining the order with another nearby project reduces trucking cost, and whether pickup is available at a lower rate. Prepare the area and clear the truck route before delivery to avoid paid labor for preventable delays.
Keep upgrades tied to the job’s actual requirements. Standard #57 stone may suit many drainage and landscaping uses, but a driveway base may need a different graded aggregate or a specified layer beneath it. Confirm the needed material with a local contractor or supplier before substituting solely to reduce the price.